Construction-Manager Preparation Store | Certification Construction-Manager Torrent
If your answer is yes then you need to start Channel Partner Program Construction-Manager test preparation with CMAA Construction-Manager PDF Questions and practice tests. With the ActualTorrent Channel Partner Program Certified Construction Manager (CCM) Construction-Manager Practice Test questions you can prepare yourself shortly for the final Certified Construction Manager (CCM) Construction-Manager exam.
Constant improvements are the inner requirement for one person. You should constantly update your stocks of knowledge and practical skills. So you should attend the certificate exams such as the test Construction-Manager certification to improve yourself and buying our Construction-Manager latest exam file is your optimal choice. Our Construction-Manager Exam Questions combine the real exam's needs and the practicability of the knowledge. The benefits after you pass the test Construction-Manager certification are enormous and you can improve your social position and increase your wage.
>> Construction-Manager Preparation Store <<
CMAA Construction-Manager Exam | Construction-Manager Preparation Store - Most Reliable Website for you
Our CMAA Construction-Manager exam questions will correct your learning problems with the help of the test engine. All contents of Construction-Manager training prep are made by elites in this area rather than being fudged by laymen. Let along the reasonable prices which attracted tens of thousands of exam candidates mesmerized by their efficiency by proficient helpers of our company. Any difficult posers will be solved by our CMAA Construction-Manager Quiz guide.
CMAA Certified Construction Manager (CCM) Sample Questions (Q36-Q41):
NEW QUESTION # 36
While conducting an inspection of the work in progress for a design-bid-build project, a CM notices that some of the completed work does not conform to the construction documents. The FIRST thing the CM should do is
Answer: B
Explanation:
According to theCMAA Standards of Practice (Chapter 5 - Quality Management), when non-conforming work is observed, thefirst actionthe CM must take isto document the condition accurately and notify the appropriate parties. The SOP states:
"When nonconforming work is discovered, the Construction Manager shall document the condition, identify the location and extent, and promptly notify the contractor, the owner, and the design professional." The CMdoes not have authority to direct corrective work(that authority lies with the owner or design professional). Proper documentation ensures an accurate record and initiates the formal resolution process.
References (CMAA Construction Manager Documents / Study Guide):
CMAA Construction Management Standards of Practice, 2010 Edition, Chapter 5 - Quality Management, Section "Nonconforming Work Identification and Documentation." CMAA CM Study Guide, Quality Management Domain, Objective 5.3: "Identify and document nonconforming work and notify appropriate parties."
NEW QUESTION # 37
As the owner's rep, a CM is providing on-site construction management services to a municipality for their new design-build city mall project.
The state requires a 40-hour value engineering workshop for all projects over $10 million. What are the key talking points about the VE process that the CM will highlight to the city's director of public works?
Answer: A
Explanation:
Value Engineering (VE) is intended to improve value by optimizing the relationship between function, cost, and life-cycle performance. The CM would emphasize that VE is amulti-discipline reviewof project functions and alternate design solutions to reduce cost without sacrificing essential performance. In a proper VE workshop, participants from multiple disciplines review function, identify alternatives, and propose changes.
The incorrect choices are:
A is wrong because life cycle and maintenance costsshouldbe considered - VE should look beyond initial cost to long-term costs.
C is simplistic: while scope reduction is one possible result, VE is not merely scope cutting but exploring alternatives to maintain functionality at lower cost.
D is incorrect, because interfacing with the design-build team is essential - VE must involve the DB team to ensure proposed changes are implementable and integrated.
NEW QUESTION # 38
An agency CM is representing the public owner of a large, complex project with numerous site challenges.
The owner has received numerous differing site condition claims on previous projects on this site. The agency CM has reviewed the bid documents and believes the site challenges are clearly and sufficiently detailed for bidders. This is a design-bid-build, lump sum procurement. The apparent low bid is more than 10% lower than the next lowest bid, and the owner is very concerned that the apparent low bidder has not included the cost of mitigating the site challenges in its bid. What should the agency CM do?
Answer: C
Explanation:
According to CMAA's recommendedOwners Risk Reduction Techniques(when using a CM for owner's risk control), one of the CM's roles is to help the owner ensure clarity of site conditions and contract documents especially when prior history on the site includes claims for differing site conditions. The CM should engage the design team to verify whether the contract documents properly capture the known site risks in adequate detail before awarding a bid.
In a design-bid-build, lump sum contract, the contractors rely on the documents and specifications as the basis of their bids. If the apparent low bid is significantly below others (e.g., >10% lower), that discrepancy raises suspicion that the low bidder may have omitted or under-priced site risk mitigation. The CM should not directly interrogate bidders or conduct post-bid interviews that might create unfairness or violate procurement rules. Rather, the correct approach is for the CM to consult with the designer to confirm whether the bid documents adequately and clearly described the site challenges. If deficiencies or ambiguities are found, the owner may need to issue clarifications, addenda, or consider re-advertising.
Thus, the prudent and contract-compliant first step is:A. Ask the designer to verify that the technical specifications describing the site challenges in sufficient detail.
NEW QUESTION # 39
When developing schedule specifications, which of the following practices should the CM recommend to the Owner to avoid disputes regarding weatherdelays per year?
Answer: A
Explanation:
TheCMAA Standards of Practice (Chapter 4 - Time Management)specifies that project schedule specifications should clearly defineexpected normal weather delaysbased on reliable climatological data to avoid disputes. The SOP states:
"The CM should recommend use of established meteorological data sources, such as NOAA, to define the number of normal adverse weather days anticipated in the schedule specification." This ensures consistency, fairness, and transparency in contract administration. Allowing the contractor to determine weather allowances (Option B) or deferring all responsibility to external sources (Options C and D) introduces ambiguity and potential disputes.
References (CMAA Construction Manager Documents / Study Guide):
CMAA Construction Management Standards of Practice, 2010 Edition, Chapter 4 - Time Management, Section "Weather Considerations and Schedule Specifications." CMAA CM Study Guide, Time Management Domain, Objective 4.1: "Develop schedule specifications including allowances for normal weather impacts."
NEW QUESTION # 40
Program management includes the early participation of the program manager in developing and making which of the following types of decisions that become the basis of a capital improvement program?
Answer: B
Explanation:
According to CMAA's Standards of Practice (Program Management section), the program manager should participate early in the program definition stage by "developing and making the initialstrategic, technical and business decisionsthat define and become the basis for the capital improvement program." Among the options given,business decisionsdirectly match that description. Safety, staffing, and jurisdictional decisions might be part of implementation, but the foundation-setting decisions include business choices (such as scope, funding, investment priorities).
NEW QUESTION # 41
......
A whole new scope opens up to you and you are immediately hired by reputed firms. Even though the CMAA Construction-Manager certification boosts your career options, you have to pass the Construction-Manager Exam. This CMAA Construction-Manager exam serves to filter out the capable from incapable candidates.
Certification Construction-Manager Torrent: https://www.actualtorrent.com/Construction-Manager-questions-answers.html
CMAA Construction-Manager Preparation Store Now buy the two versions of our material, you will get a 50% discount, Now let's discuss the benefits you can get upon buying our Certified Construction Manager (CCM) (Construction-Manager) exam material today, CMAA Construction-Manager Preparation Store As our real time exam test engine allows you to experience as if you are in the exam hall, Most qualification certifications are in common use in most of countries in the world so do our professional Construction-Manager test questions.
The argument most often cited in favor of using this technology is Construction-Manager enhanced scalability, Learn how your customers define success, Now buy the two versions of our material, you will get a 50% discount.
Pass Guaranteed CMAA - Construction-Manager - Perfect Certified Construction Manager (CCM) Preparation Store
Now let's discuss the benefits you can get upon buying our Certified Construction Manager (CCM) (Construction-Manager) exam material today, As our real time exam test engine allows you to experience as if you are in the exam hall.
Most qualification certifications are in common use in most of countries in the world so do our professional Construction-Manager test questions, You can prepare for the Construction-Manager through practice kits without facing any problem.